BLAST FURNACE 2 RELINING
|
|
: Siderar S.A.
|
|
: Argentina
|
|
: 14/09/1995
|
|
: Reline blast furnace 2, at the General Savio Steel plant, 5,800 tn/day capacity. The works include: new furnace profile, higher internal volume, higher operation pressure, raw material clasification, new control and instrumentation system, new fume collecting and treatment system, gas treatment system and auxillary installations.
|
|
: Detail engineering, procurement services, instrumentation and electromechanical erection
|
|
|
|
|
|
|
|
| |